n1A CONTRIBUTION TO EXPLORATION FOR CONSTRUCTION OF WATERPROOF SCREEN ON OPEN PIT MINE “DRMNO” n1PRILOG ISTRAŽIVANJU IZGRADNJE VODONEPROPUSNOG EKRANA NA POVRŠINSKOM KOPU DRMNO
n2Šubaranović Tomislav, Ilić Saša, Krstović Slobodanka n2Šubaranović Tomislav, Ilić Saša, Krstović Slobodanka
n3ABSTRACT n3IZVOD
n4In the paper is given review of results from additional geologic explorations, based on produce of three exploration boreholes in period from January to March 2006 for requirement of waterproof screen construction in open pit mine "Drmno". n4U radu je dat prikaz rezultata dopunskih geoloških istraživanja na osnovu izrade tri istražne bušotine u peri-odu od januara do kraja marta 2006. godine za potrebe izrade vodonepropusnog ekrana na površinskom kopu Drmno.
n5Key words: waterproof screen, open pit mine, boreholes n5Ključne reči: vodonepropusni ekran, površinski kop, bušotine.
n6INTRODUCTION n6UVOD
n7After determining location for waterproof screen construction in open pit coal mine Drmno, as gathering all relevant hydrologic, hydro-geologic and geomechanical characteristic of deposit, then was started additional terrain exploration, that is creation of three exploration bore-holes (2 hydrogeologic and 1 hydrologic-geomechanic). n7Nakon određivanja lokacije za izradu vodonepropusnog ekra-na na površinskom kopu uglja Drmno, kao i prikupljanja svih rele-vantnih hidroloških, hidrogeoloških i geomehaničkih karakte-ristika ležišta, pristupilo se dodatnom terenskom istraživanju koje se sastojalo u izradi tri istražne bušotine (2 hidrogeološke i 1 hidrogeološko geomehanička).
n8METHODOLOGY AND CIRCUMFERENCE OF PERFORMED EXPLORATIONS n8METODOLOGIJA I OBIM IZVEDENIH ISTRAŽIVANJA
n9At this phase of exploration in determined location (Figure 1 and 2) are accomplished 3 exploration boreholes P-12, P-13 and P- 16, what are consistent with adopted Project of geologic exploration on open pit mine Drmno (Faculty of Mining and Geology, Belgrade). n9U ovoj fazi istraživanja na određenoj lokaciji (slika 1.) izvedene su 3 istražne bušotina P-12, P-13 i P-16, koje su uskla-đene sa usvojenim Projektom geoloških istraživanja površinskog kopa Drmno (Rudarsko-geološki fakultet, Beograd).